1 A, B and C can complete a piece of work in 24, 6 and 12 days respectively. Working together, they will complete the same work in:
 
1124day
2724day
3337day
44 days
 
Answer: Option3
2 60 men could complete a work in 250 days. They worked together for 200 days. After that the work had to be stopped for 10 days due to bad weather. How many more men should be engaged to complete the work in time?
 
110
215
318
420
 
Answer: Option2
3 A and B can together finish a work 30 days. They worked together for 20 days and then B left. After another 20 days, A finished the remaining work. In how many days A alone can finish the work?
 
140
250
354
460
 
Answer: Option4
4 A can do a certain work in the same time in which B and C together can do it. If A and B together could do it in 10 days and C alone in 50 days, then B alone could do it in:
 
115 days
220 days
325 days
430 days
 
Answer: Option3
5 5 men and 2 women working together can do four times as much work per hour as a man and a woman together. The work done by a man and a woman should be in ratio:
 
1 1:2
22:1
3 1:3
44:1
 
Answer: Option2
6 A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day?
 
112 days
215 days
316 days
418 days
 
Answer: Option2
7 A and B can do a work in 18 and 24 days respectively. They worked together for 8 days and then A left. The remaining work was finished by B in:
 
15 days
216/3 days
38 days
410 days
 
Answer: Option2
8 If 6 men and 8 boys can do a piece of work in 10 days and 26 men and 48 boys can do the same in 2 days, the time taken by 15 men and 20 boys to do the same type of work will be:
 
15 days
24 days
3 6 days
4 7 days
 
Answer: Option2
9 Sakshi can do a piece of work in 20 days. Tanya is 25% more efficient than Sakshi. The number of days taken by Tanya to do the same piece of work is:
 
115
216
318
425
 
Answer: Option2
10 1 A road of 5 km length will be constructed in 100 days. So 280 workers were employed. But after 80 days it was found that only 3km road was completed Now how many more people were needed to finish the work in the specified time?
 
1480
280
3200
4100
 
Answer: Option3